05/05/2017 - POOL - Solar heating installed on roof
01/05/2017 - POOL - Pool coping concrete installed to hold pool in place
28/04/2017 - BUILD - Appliances, heating/cooling installed. Pool equipment installed
27/04/2017 - POOL - Pool lowered into hole
26/04/2017 - POOL - Pool hole finished excavation and pool delivered
24/04/2017 - OTHER - Quote for office cabinetry and glass pet door installed.
24/04/2017 - OTHER - LHS Fence completed
24/04/2017 - POOL - Pool construction starts
22/04/2017 - OTHER - LHS Fence started
20/04/2017 - OTHER - Driveway construction finishes
18/04/2017 - OTHER - Driveway construction starts
12/04/2017 - OTHER - Blinds Installed
07/04/2017 - BUILD - Received Keys and Handover Completed
31/03/2017 - BANK - Final Progress Payment Paid
31/03/2017 - BUILD - Follow up on QA Inspection
27/03/2017 - BUILD - QA Inspection with Independent Inspector
17/03/2017 - BUILD - Most fixtures and fittings installed.
17/03/2017 - BUILD - Carpet Laid
10/03/2017 - POOL - Receive building permit for pool
10/03/2017 - BUILD - Electrical Works Start - Tiling completed
06/03/2017 - BUILD - All tiles laid and ready for mortar
02/03/2017 - BUILD - Floor leveling completed. Tiling starts. Glass splash-back installed in kitchen
22/02/2017 - BUILD - Caesarstone benches installed. Floor leveling for the tiling starts.
15/02/2017 - POOL - Rainwise lodge building permit in preparation for construction in March/April.
13/02/2017 - BUILD - First coats of painting have occured. Front Facade has been rendered
13/02/2017 - OTHER - Meeting on site with Fence company to arrange fence quote.
09/02/2017 - OTHER - Meeting on site with Concreting company to arrange driveway quote.
08/02/2017 - BUILD - Plastic put up in windows in preparation of painting starting.
02/02/2017 - OTHER - Meeting on site with Blind company to measure and choose colours
02/02/2017 - BUILD - PrePlaster/Waterproofing inspection takes place
17/01/2017 - BUILD - Cement sheeting installed in eaves.
16/01/2017 - BUILD - Kitchen and Bathroom cabinetry installed
16/01/2017 - BUILD - Skirting installed around windows and all internal doors hung.
13/01/2017 - BUILD - Plaster and cornice inside completed
06/01/2017 - BANK - Progress payment for external lock up received and paid.
24/12/2016 - BUILD - External lock up stage achieved (brick work complete)
15/12/2016 - BANK - Progress payment for frame stage received and paid.
15/12/2016 - BUILD- Plaster commences inside and Bricks start getting laid.
12/12/2016 - BUILD- Insulation installed
09/12/2016 - BUILD - Most plumbing and electrical completed. Insulation installed
09/12/2016 - BUILD - Independent inspection completed on Pre-plaster stage
07/12/2016 - BUILD - Bricks delivered to site.
02/12/2016 - BUILD - Roof installed and plumbing and electrical starts
27/11/2016 - BUILD - Gutters installed and roof tiles delivered to site
21/11/2016 - BUILD - Independent inspection completed on Slab/Frame stages
18/11/2016 - BUILD - Frame reaches completion
15/11/2016 - BUILD - Frame construction starts
07/11/2016 - BANK - Progress payment for slab stage received and paid
05/11/2016 - BUILD - Slab pour completed
03/11/2016 - BUILD - Slab foundation laid
29/09/2016 - BUILD - First signs of digging and site works
13/09/2016 - BUILD - Fence placed around block in preparation of works.
07/09/2016 - BUILD - Build file passed to construction phase
02/09/2016 - BUILD - Final quality assurance checks of build completed
29/08/2016 - BUILD - Received building permit from Council
23/08/2016 - BANK - Received formal loan approval for Land and Build
11/08/2016 - BUILD - Received developer approval for build
20/07/2016 - BANK - Meeting with mortgage broker to sign formal loan paperwork
19/07/2016 - BANK - Received formal finance for Land/Construction/Pool Loan
13/07/2016 - BANK - Valuation of Land and build takes place
23/06/2016 - LAND - Land settles and land loan matures
16/06/2016 - LAND - Land construction finishes and Titles
10/06/2016 - BANK - Signed formal loan documents for Land with broker
08/06/2016 - BANK - Received formal loan approval for land
12/05/2016 - POOL - Sign contracts for Pool and paid deposit
05/04/2016 - POOL - Meeting with Rainwise Pools to discuss pool quote
16/03/2016 - BUILD - Electrical Appointment at Boutique Head Office
10/03/2016 - BUILD - Colour Appointment and Contract Signing at Boutique Head Office
03/02/2016 - BUILD - Walked through Hynes Tiles to see Full Range
15/01/2016 - BANK - Received conditional approval for Land + Construction Loan
13/01/2016 - BUILD - Signing of PWC (Preliminary Works Contract) at Boutiqe Head Office
08/01/2016 - BUILD - Completed second walk through of St Tropez
03/01/2016 - BUILD - Completed first walk through of St Tropez 28 Display Home
23/11/2015 - LAND - Balance of 10% of land purchase paid to developer
18/11/2015 - LAND - Signed land contracts and paid further $10,000 deposit to confirm purchase
16/11/2015 - LAND - Received contracts and sent to conveyancer to read over
15/11/2015 - BANK - Contacted mortage broker and arranged conditional approval for land loan
15/11/2015 - LAND - Placed $1000 deposit to secure place in development release
19/07/2016 - BANK - Received formal finance for Land/Construction/Pool Loan
13/07/2016 - BANK - Valuation of Land and build takes place
23/06/2016 - LAND - Land settles and land loan matures
16/06/2016 - LAND - Land construction finishes and Titles
10/06/2016 - BANK - Signed formal loan documents for Land with broker
08/06/2016 - BANK - Received formal loan approval for land
12/05/2016 - POOL - Sign contracts for Pool and paid deposit
05/04/2016 - POOL - Meeting with Rainwise Pools to discuss pool quote
16/03/2016 - BUILD - Electrical Appointment at Boutique Head Office
10/03/2016 - BUILD - Colour Appointment and Contract Signing at Boutique Head Office
03/02/2016 - BUILD - Walked through Hynes Tiles to see Full Range
15/01/2016 - BANK - Received conditional approval for Land + Construction Loan
13/01/2016 - BUILD - Signing of PWC (Preliminary Works Contract) at Boutiqe Head Office
08/01/2016 - BUILD - Completed second walk through of St Tropez
03/01/2016 - BUILD - Completed first walk through of St Tropez 28 Display Home
23/11/2015 - LAND - Balance of 10% of land purchase paid to developer
18/11/2015 - LAND - Signed land contracts and paid further $10,000 deposit to confirm purchase
16/11/2015 - LAND - Received contracts and sent to conveyancer to read over
15/11/2015 - BANK - Contacted mortage broker and arranged conditional approval for land loan
15/11/2015 - LAND - Placed $1000 deposit to secure place in development release