Sunday, March 26, 2017

QA Inspection

We have just got back from our QA inspection with our building inspector present. Overall we are really excited that we are in the final stages and happy with the quality of the home at present. We have been told that we should have our New Home Presentation this coming Friday. There were not many majors items picked up however quite a lot of small dents and scratches which is too be expected.

Below is a list of points that need rectifying.

- Missing towel rail and door handle in Ensuite
- Missing sink taps and towel rails in powder room
- Missing shower screen in main bathroom.
- Walls in bedroom, powder room, living and dining still need to be patched.
- Alarm system still needs to be installed
- Missing flood light on garage wall.
- Missing man hole in garage.
- Big chip in one of the tiles in the ensuite.
- Door and window tracts need a big clean out and detail.
- Some minor repainting required.
- 2 light switches and 1 light not working.
- Missing gas point on garage wall for future pool install.
- Some minor mortar cracking issues on the exterior.
- Silicon on a coupe of tiles that needs a proper clean off
- One of the bedrooms has a big lump under the carpet.
- Media room is missing lower wall HDMI power socket.
- Mirrors will be installed with appliances after NHP
- Pendant lights above kitchen island bench not installed.

Please see photos below.

Front Facade
Garage - Missing man hole.
Office
Ensuite. Note missing sliding door handle, towel rail and mirror
Chipped tile in Ensuite
Closeup of chipped Tile
Walk in robe in Main Bedroom
Looking towards front entry from living.
Looking towards living from Front Door
Living/Kitchen. Roof where the vent was moved needs patching
Kitchen splashback
Dining
Walk in pantry
Looking towards powder and main bathroom from dining 
Main bathroom - Missing shower screen 
Main bathroom
Laundry
Laundry
Wall needs patching and tape on floor marks area where
 there is a large bump under the carpet 

Saturday, March 18, 2017

Progress update before QA inspection

Just a quick photo update before the QA inspection this coming Thursday. Should only be a week or two away now!

Powder room sink 
Laundry

Ensuite

Shower in ensuite

Ensuite
Ensuite sinks
Main bedroom

Bathroom shower


Kitchen sink

Kitchen
Living room
Lighting in Living


Front door


Hallway to living

Garages
Facade


Monday, March 6, 2017

Caesarstone, Splashback and Tiling

In my last post I outlined some issues we were having with our build and the quality being picked up by our inspectors. As a result of raising my concerns with Boutique an on site meeting and walk through was arranged so the Regional Building Manager could walk me through the build and explain how and what they would be doing to fix the issues.

The walk took around an hour and the RBM took the time to go through each point one at a time to make sure I understood the issue and how it would be fixed. It really helped put my mind at ease regarding some of these issues.

I also took this opportunity to point out some other smaller issues that I had noticed that I wanted addressed. Things like cracked door frame, wrong colour walls and curved or bowed skirting. All of which the RBM assured me would be fixed.

At this stage of the build the floor leveling had started in preparation of the tilers starting. This involved grinding down raised sections of the concrete slab or raising it up by using self leveling mortar. They also prepared the shower bases.

Slab being ground down so it would be more level

A few days later we had a peak through the windows and noticed the Caesarstone benches in the ensuite, bathroom and kitchen had been installed. It was an awesome surprise as we were under the impression it was still weeks away and we had been hanging out to get a look at it!

Caesarstone bench in Fresh Concrete

Ensuite Caesarstone in Raw Concrete

Main bathroom Caesarstone in Fresh Concrete
Not long after that surprise the tiling started. They started on a Friday and managed to get all tiles laid by Monday by working on the Saturday. This included the ensuite, bathroom and laundry splashbacks. All they have to do now is add the grout!

Dining Room - Galileo Disk Grey Glazed Porcelain 600X600

Looking towards powder room and bathroom

Looking towards laundry

Dining Room
The only downside we experienced over the lasts couple of weeks was the cladding on the facade. It appears that the wrong material has been ordered and instead of an horizontal cladding installed around the main bedroom window it was vertical. It looked weird from the moment we saw it and as soon as I raised this with the RBM he advised that he would chase up the correct material. Hopefully that is installed over the next week or so.

Vertical style cladding. Should be horizontal
From here they will grout all the tiles and then start the electrical works. Shower screens and basic fittings will also be installed. Carpet will be later on and the last coats of paint will be finished a couple of days before the pre-completion inspection. We have been asked to book in our PCI with our independent inspector on the 23rd of March. Fingers crossed for minimal issues and a sooner rather than later completion date!

Wednesday, February 15, 2017

Painting/Facade and other quotes.

It has been around 4 weeks since the last update. For the first 2 weeks not a lot happened. However since then there have been a few changes and all of a sudden the waterproofing was done, the first part of the painting has been completed and the front facade has been rendered.

It all started back on Feb 2nd. Waterproofing had been completed and the plaster prepared for painting. We arranged for our independent inspector to complete a visit to check the build before the next steps.

Unfortunately when I received the inspection report back it was very disheartening to see many issues which had already been listed on previous reports. I couldn't understand why these wouldn't have been fixed yet so I typed up an angry email to our client liaison.

The 4 main points I had issues with were as follows.

- Vapor barrier to protect the slab from the weather had not been rectified. This had now been picked up on 3 different independent inspections over a 3 month period.

- The roof, bricks and gutters had all be completed the gutters had been left very full of rubbish and mortar. Had been picked up on previous inspections.

- Temp down pipes to stop water splashing everywhere when it rained had never been installed even though it had been mentioned in two different inspection reports.

- Walls were checked during the pre-plaster inspection and found to be bowed and not straight. It was mentioned that the frame would be fixed prior to plaster however apparently it wasn't, meaning that we now have multiple walls which have visible bends.


Within an hour I received a phone call back from the Regional Construction Manager basically saying that there had been a few issues and he would be taking over our build supervision personally.

Since that day the painting began (without fixing the walls no not sure what they are going to do about that) and the front facade was rendered.





I had also had another good phone call with the Regional Manager who managed to put my mind at ease about a few things and we have arranged to catch up on site next week so he can personally go through the inspection report to explain them. I'll provide an update to this walk through next week.

In between all of the above happening we also had to arrange appointments on site with Into Blinds, Melbourne Fencing Specialists and A Better Driveway. It was a bit of a juggling act however we have managed to finalise our blind quote and arrange quotes for the fence and driveway.

Fencing

For our fencing needs we have a total of 89 linear meters. This includes a 3.5m fence and gate from the garage to the boundary.

For a double paling fence at that distance and a gate the total project comes to $11,150 with our share being $6,038.

The fence quote was always going to be more expensive than normal as we require double sided palings which means there will be no rails to climb on either side of the fence. As we have a swimming pool we really want to make sure that kids can't climb over the fence from our neighbors property or use the railings to climb over the pool fence on our side.

It looks like we will go with this quote as we were very happy with their service during the quote. They will also assist with sending out Notices to Fence to our 5 neighbouring blocks so we won't have to worry about chasing them up ourselves.

Driveway

For our driveway needs we have a total of 154m2. This includes around 25m2 for our sideway. Because our garage is set back 10m on the long side and we have a 3 car garage we always knew this would be expensive. We have also extended the width to cover down the side of the home beside the garage to so we have some extra parking for guests. This effectively means we will have a driveway that is 4 car widths wide.

We will be choosing a charcoal colour exposed aggregate which means the expected price is $13,777. Pretty expensive however considering the amount we need it is acceptable. It works out to be around $89 per square meter which is pretty average for exposed aggregate.

Blinds

In a previous blog post I went through our blind details.

http://tropezienadventure.blogspot.com.au/2016/12/blind-quote.html

During our meeting with the installer they just came out to take some final measurements and help us choose colours so they could start production and have the blinds ready for hand over.

It was lucky that they did come out as it turns out when the salesman did our initial quote off the plans he wrote the numbers backwards so all the blinds would have been wrong.

We have also chosen to add a small blind to the glass window beside the front door. Initially we were going to leave this clear so we could see out however seeing how wide it is in person and how visible it makes the inside of the house we will add a blind for privacy. We can still see who is at our door by opening the blind first.
You can see the window to the right of the door. Wider than we thought.
Finally, as it turns out we are not allowed to excavate the pool until the house is finished and handed over. This was a real bummer as we had our hopes high after the discussion with our previous supervisor.

Being allowed to have the pool excavated before hand over would mean that soon as it is handed over and we are able to move in we can get the driveway and fence installed. At the moment we can't get the fence installed before the pool as they need the access and we can't have the driveway installed as the pool excavation trucks will damage it.

It is a bit of a catch 22 however we will keep working on Boutique and see if they can came around! Hopefully our neighbours on the North side of us don't start building soon so we can use their land to gain access to the pool area!

Wednesday, January 18, 2017

External Lockup and pre-painting

It has been a few weeks since our last post. A busy time at work in the lead up to Christmas and then we managed to get away to QLD for New Years which was nice and relaxing!

Just before Christmas Boutique managed to reach external lock up and finish the plastering inside. It was good to see that they also worked through Boxing day and the days between Christmas and New Years to finish some smaller jobs.

Since New Years they have completed a lot of work and we were able to see it all today with a site tour with our build supervisor. Stephen was fantastic and gave us all the time we needed to have a good look around. I believe we were there for nearly 45 minutes and he never tried to wrap it up at all!

The items we saw completed are as follows.

- All plastering except for the garage is complete. They are hoping to complete the garage this week.
- They have added skirting boards to all the walls and finished and prepared the square set cornice for painting.
- They have prepared the plaster walls for painting by sanding back the walls to a smooth finish.
- All external brick work is complete except for the front facade which is just waiting for a fascia plate and cladding.
- They have installed the cement sheeting in the eaves.
- Cabinetry has been delivered and installed in all rooms (Kitchen/Bathrooms/Laundry) Just waiting for the caesar stone and appliances.
- All internal doors and frames have been hung. The proper front door has also been installed.

During our site visit we also got to talking about the next stages of the build. Hopefully at the end of this week all pre-painting and waterproofing work will be finished. We will have our independent inspector go through early next week and then over the next couple of weeks should see all the painting completed.

After the painting all they need to do is lay the tiles and carpet, door handles and electrical switches/lights and install appliances.

Our site supervisor goes on leave on the 5th of March and he is hoping to have everything complete and handed over before then. He is also going to try to get approval for us to get the pool company in before handover to excavate the area ready for pool installation!

Below are some photos of the kitchen and ensuite cabinetry. You can see the square set cornices in a few of the photos and we think they look great!




Ensuite

Ensuite